DELIVERY ORDER

THE CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND WORK NECESSARY TO INSTALL AN AREA LIGHTING CIRCUIT, CONCRETE PAD, AND SECURITY FENCING FOR THE NEW SECURED AREA OUTSIDE THE E

Awarded to OLGOONIK ENTERPRISES, LLC

PIID FA251722F0197US · USAspendingConstruction
$109.5K
Data last updated Oct 22, 2026 · Source: USAspending
Transaction obligation$109,480sum disclosed on award record
Current contract valueNot reportednot interchangeable with obligation
Potential contract valueNot reportedincluding options if reported
Award dateSep 19, 2022
Company legal name
OLGOONIK ENTERPRISES, LLC
UEI / CAGE
NTJRK3T2CKN7 / Not reported
Parent award
Not reported
Awarding agency
Department of Defense
Subagency
Department of the Air Force
Industry
Construction
NAICS
236220
PSC
Z2EA
Performance period
Not reported — Not reported
Recipient address
411 S TEJON ST STE G, COLORADO SPRINGS, EL PASO, CO, 80903
Place of performance
COLORADO SPRINGS, EL PASO, CO, 80914
Source last modified
Nov 3, 2026

Description

THE CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND WORK NECESSARY TO INSTALL AN AREA LIGHTING CIRCUIT, CONCRETE PAD, AND SECURITY FENCING FOR THE NEW SECURED AREA OUTSIDE THE EOD SECTION OF BUILDING 625 AT PETERSON SPACE FORCE BASE

View federal source ↗

Derived from official transactions

Contract lifecycle

  1. Award announced

    THE CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND WORK NECESSARY TO INSTALL AN AREA LIGHTING CIRCUIT, CONCRETE PAD, AND SECURITY FENCING FOR THE NEW SECURED AREA OUTSIDE THE E

    US · usaspendingSource ↗
  2. Value increased

    THE CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND WORK NECESSARY TO INSTALL AN AREA LIGHTING CIRCUIT, CONCRETE PAD, AND SECURITY FENCING FOR THE NEW SECURED AREA OUTSIDE THE E

    US · usaspending$109.5KSource ↗

Point-in-time model

Contract change outlook

Predictive intelligenceInsufficient historyNo eligible point-in-time model has produced a prediction for this record.

Uncollapsed source history

Transactions and modifications

Action dateModificationAction typeExact obligationCurrent totalPotential totalDescriptionSource
Sep 16, 20220Not reported$109,480.00Not reportedNot reportedTHE CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, AND WORK NECESSARY TO INSTALL AN AREA LIGHTING CIRCUIT, CONCRETE PAD, AND SECURITY FENCING FOR THE NEW SECURED AREA OUTSIDE THE EOD SECTION OF BUILDING 625 AT PETERSON SPACE FORCE BASEUSAspending ↗