PROJECT NUMBER 23-2216 CONCEPT DESIGN INSTALL ELEVATOR AT BUILDING 10577.

Awarded to POND-CDM SMITH JV LP

PIID FA461024F0106US · USAspendingOther
$220.2K
Data last updated Oct 22, 2026 · Source: USAspending
Transaction obligation$220,150sum disclosed on award record
Current contract valueNot reportednot interchangeable with obligation
Potential contract valueNot reportedincluding options if reported
Award dateJun 10, 2024
Company legal name
POND-CDM SMITH JV LP
UEI / CAGE
JJH2R5GX4WL7 / Not reported
Parent award
Not reported
Awarding agency
Department of Defense
Subagency
Department of the Air Force
Industry
Other
NAICS
541330
PSC
C211
Performance period
Not reported — Not reported
Recipient address
3500 PARKWAY LN STE 500, PEACHTREE CORNERS, GWINNETT, GA, 30092
Place of performance
LOMPOC, SANTA BARBARA, CA, 93437
Source last modified
Oct 23, 2026

Description

PROJECT NUMBER 23-2216 CONCEPT DESIGN INSTALL ELEVATOR AT BUILDING 10577.

View federal source ↗

Derived from official transactions

Contract lifecycle

  1. Contract modified

    PROJECT NUMBER 23-2216 CONCEPT DESIGN INSTALL ELEVATOR AT BUILDING 10577.

    US · usaspendingSource ↗
  2. Contract modified

    PROJECT NUMBER 23-2216 CONCEPT DESIGN INSTALL ELEVATOR AT BUILDING 10577.

    US · usaspendingSource ↗
  3. Contract modified

    PROJECT 23-2216 CONCEPT DESIGN INSTALL ELEVATOR AT B10577. THE ARCHITECT-ENGINEER (A-E) SHALL CONDUCT FIELD INVESTIGATIONS AND PREPARE A COMPLETE AND USABLE CONCEPT DESIGN IN ACCOR

    US · usaspendingSource ↗
  4. Contract modified

    PROJECT NUMBER 23-2216 CONCEPT DESIGN INSTALL ELEVATOR AT B10577

    US · usaspendingSource ↗
  5. Award announced

    XUMU 23-2216 CONCEPT DESIGN INSTALL ELEVATOR AT B10577. THE ARCHITECT-ENGINEER (A-E) SHALL CONDUCT FIELD INVESTIGATIONS AND PREPARE A COMPLETE AND USABLE CONCEPT DESIGN IN ACCORDAN

    US · usaspendingSource ↗
  6. Value increased

    XUMU 23-2216 CONCEPT DESIGN INSTALL ELEVATOR AT B10577. THE ARCHITECT-ENGINEER (A-E) SHALL CONDUCT FIELD INVESTIGATIONS AND PREPARE A COMPLETE AND USABLE CONCEPT DESIGN IN ACCORDAN

    US · usaspending$220.2KSource ↗

Point-in-time model

Contract change outlook

Predictive intelligenceInsufficient historyNo eligible point-in-time model has produced a prediction for this record.

Uncollapsed source history

Transactions and modifications

Action dateModificationAction typeExact obligationCurrent totalPotential totalDescriptionSource
Jun 5, 2025P00004BNot reportedNot reportedNot reportedPROJECT NUMBER 23-2216 CONCEPT DESIGN INSTALL ELEVATOR AT BUILDING 10577.USAspending ↗
Apr 14, 2025P00003BNot reportedNot reportedNot reportedPROJECT NUMBER 23-2216 CONCEPT DESIGN INSTALL ELEVATOR AT BUILDING 10577.USAspending ↗
Mar 11, 2025P00002BNot reportedNot reportedNot reportedPROJECT 23-2216 CONCEPT DESIGN INSTALL ELEVATOR AT B10577. THE ARCHITECT-ENGINEER (A-E) SHALL CONDUCT FIELD INVESTIGATIONS AND PREPARE A COMPLETE AND USABLE CONCEPT DESIGN IN ACCORDANCE WITH STATEMENT OF WORK (SOW) DATED 11 APRIL 2024.USAspending ↗
Feb 21, 2025P00001BNot reportedNot reportedNot reportedPROJECT NUMBER 23-2216 CONCEPT DESIGN INSTALL ELEVATOR AT B10577USAspending ↗
Jun 3, 20240Not reported$220,150.49Not reportedNot reportedXUMU 23-2216 CONCEPT DESIGN INSTALL ELEVATOR AT B10577. THE ARCHITECT-ENGINEER (A-E) SHALL CONDUCT FIELD INVESTIGATIONS AND PREPARE A COMPLETE AND USABLE CONCEPT DESIGN IN ACCORDANCE WITH STATEMENT OF WORK (SOW) DATED 11 APRIL 2024.USAspending ↗